A big data center can claim a sealed cooling system that doesn’t touch local water supplies and still leave a heavy water footprint elsewhere, argues a researcher who studies water management in Canada’s Prairie region.The example is a Bell Canada AI data center near Regina, Saskatchewan, billed as the largest private-sector capital investment in Canadian history. When fully operational, it will need up to 1.2 gigawatts of electricity: 300 megawatts from the provincial grid and 900 megawatts from an on-site, bring-your-own-power setup.What the company saysBell Canada says the facility will use energy responsibly “without competing for local power resources.” It says the data center will use a sealed, closed-loop water-cooling system with air-cooled heat rejection, not connected to groundwater or the municipal supply.Residents have still raised concerns about water and electricity use. The author notes the closed-loop design counts only the water used to run the building, not the water used to generate its power.Dry cooling versus wet coolingDry cooling uses large fans and radiators to move heat into the air and generally takes more electricity. Wet cooling relies on water’s high latent heat of vaporization, much like sweating, so it needs a steady supply of water to carry waste heat away. Data centers and power plants face the same trade-off.Power is the other half of the equationMost electricity generation remains highly water-intensive. A 2024 Lawrence Berkeley National Laboratory study estimated that U.S. data centers’ indirect water use, meaning the water used to generate their electricity, was about 211 billion gallons in 2023.In Saskatchewan, about 25% of generating capacity is coal, according to SaskPower’s 2025-26 annual report. If the grid supplies 300 megawatts to the data center, cooling water will still be used at power plants far from Regina. The province’s coal plants use a mix of dry and wet cooling, and small modular reactors proposed along the Rafferty Reservoir would need similar cooling. The government plans to refurbish and extend three coal plants, Poplar River, Shand and Boundary Dam, as a bridge until planned nuclear reactors come online.The takeaway, the author argues, is that closed-loop cooling cuts on-site demand but shifts water use somewhere else, potentially increasing total withdrawals from ecosystems far from the data center. To get the full picture, operators would need to count both on-site use and the water used to make the electricity.If the province follows Alberta and burns natural gas for data centers, water is needed to drill, extract, process and deliver the gas. Saskatchewan produces relatively little natural gas, so much of it would likely come from Alberta fields.A region of feast and famineThe Prairies swing widely in precipitation and temperature, so the water entering reservoirs in the Assiniboine River basin can change from year to year, while demand from industry, power generation, agriculture and cities doesn’t flex with it.More research is needed on how water enters soils during spring snowmelt and how wetlands fill and spill into streams. Authorities will need to weigh the cumulative effects of added demand, especially in prolonged droughts.