Infamously called Bengaluru’s ‘Stonehenge‘ project for the unfinished concrete pillars abandoned in the middle of busy roads for years, the Ejipura flyover is unlikely to be completed even by early 2027, as pending land acquisition continues to stall construction.The Ejipura flyover, a 2.38-km elevated corridor with entry/exit ramps on the Inner Ring Road and the Koramangala Kendriya Sadan near the Hosur Road Junction, is intended to streamline traffic flow between the Inner Ring Road and Koramangala to the National Highway on Hosur Road. However, the project, initiated in 2017 with an initial estimated cost of Rs 158 crore and supposed to be completed by 2019, missed several deadlines and has often been criticised by the public.Greater Bengaluru Authority (GBA)’s chief engineer Raghavendra Prasad, who has been overseeing the Ejipura flyover, told The Indian Express, “The work has progressed considerably, and we are targeting to complete the right-side stretch by the end of December 2026.”However, land acquisition has remained a significant challenge, especially near St John’s Hospital. Prasad said that they have successfully acquired some land from the hospital, but additional land is still required. Meetings regarding the acquisition are ongoing.Another official said the ramp on the Madiwala side has been completed. Sources indicate that while the project is 82 per cent complete, the area has turned into a garbage dump and has become congested with traffic. A man sleeping at the Ejipura flyover construction site (Express photo).What the progress report showsAccording to sources, BSCPL Infrastructure, the present contractor, was supposed to complete the project by February 2025. But there has been a delay; the viaduct is 2.09 km long, and about 1.94 km has been completed.Story continues below this adA progress report accessed by Indian Express showed that segment casting and all five portal beams are complete. Of 629 balance segments, 582 have been erected, leaving 47. Forty-nine of 54 spans are done. Foundation works are slower. Only 39 of 71 balance piles, 13 of 21 pile caps, 13 of 21 pier shafts and six of 15 pier caps are finished. Drains are 39 per cent complete and footpaths 38 per cent.Reinforced earth panels are 67 per cent cast and 42 per cent erected. Crash barriers are 4 per cent done and expansion joints 39 per cent, while the median, mastic asphalt and structure painting have not begun.Commuters and traffic police flag daily delaysFor people who use the stretch regularly, the delay is not just about a project on paper. Sagar, a commuter who regularly travels through Ejipura, said, “Initially, the government had not planned the flyover properly. If everything had been planned well from the beginning, it would not have taken so much time. That is why the work has been delayed.”“The flyover could ease congestion during evening peak hours, particularly for commuters heading towards Hosur Road. However, those travelling towards Koramangala would still have to use the underpass and wait at the junction,” he added.Story continues below this ad Pothole filling work going on at the Ejipura flyover (Express photo).“Initially, we did not pay much attention to the project because the flyover was expected to connect directly to the Ring Road extension, but all it brought was construction dust and noise, and we want the work to be completed soon. Given Ejipura’s connectivity to areas such as Domlur, HAL, Marathahalli and Whitefield, an integrated Metro and flyover plan would have served commuters better,” said Lohit Narayan, a resident of Ejipura.Sandeep Anirudhan, convener of the citizens movement Bengaluru Mobility, said, “The proposed project was unsuitable and unlawful because it did not align with the city’s master plan. The high-density corridor should have been developed as a mass transit project, such as a metro or light rail system.”Ashok Nagar traffic inspector Faaroq Pasha said, “Waterlogging during the rains and water flowing from defence land has been causing problems for commuters around the Ejipura flyover junction”.“We have asked the contractor and the GBA to provide a permanent solution to the waterlogging,” Pasha said. He also said traffic was being managed alongside various ongoing projects in the area, including the B-SMILE buffer-zone initiative to construct roads along stormwater drains and lake buffer zones.Thejaswini N is an intern with The Indian Express.