Man booked a flat in Mumbai in 2010 but didn't get possession as builder sold it to third party; he approached MahaRERA and won full refund with interest, penalty on developer

Wait 5 sec.

While the developer issued an allotment letter dated August 16, 2010, it failed to provide possession to the buyer. In view of the delay, the homebuyer had approached Maharashtra RERA seeking relief. The authority had on April 24, 2025, ordered the relief of possession to the homebuyer. He again filed a review seeking refund of the amount.